当前位置:首页计算机类软件水平考试高级信息系统项目管理师->Inthe()phaseteammembersbeginto

In the ( ) phase team members begin to work together and adjust their work habits and behaviors to support the team.The team learns to trust each other.

  • A.storming
  • B.performing
  • C.norming
  • D.adjourning
查看答案 纠错
答案: C
本题解析:

翻译:在规范阶段,团队成员开始一起工作并调整自己的工作习惯和行为支持团队。团队成员学会互相信任。A.震荡 B.执行 C.规范 D.休息

更新时间:2021-12-02 18:40

你可能感兴趣的试题

单选题

Some team leaders think that the only way to ( )their team is through cash incentives. However research proves that money is the last thing you would want to use.

  • A.arouse
  • B.encourage
  • C.incite
  • D.motivate
查看答案
单选题

Cloud computing provides on-demand service to users by using distributed computing and( )resource management.

  • A.network
  • B.virtual
  • C.centralized
  • D.specializeD
查看答案
单选题

Cloud-computing providers offer their“services”according to differentmodels,which happen to form a stack( ),platform as a service(Paas),software as a service(SaaS).

  • A.hardware as Aservice(Haas)
  • B.network as A.service(Naas)
  • C.infrastructure as A.service(IaaS)
  • D.datA.as A.service(DaaS)
查看答案
单选题

( ) is used to model aggregates of information and the relationships these aggregates have to other.

  • A.DatAflow diagram
  • B.Entity relationship diagram
  • C.Sequence diagram
  • D.Structure diagram
查看答案
单选题

Your project is behind schedule due to conflict between team members. Having resolved the conflict,to get the project back on schedule,you should consider ( ) .

  • A.crashing the schedule
  • B.performing resource leveling
  • C.conducting reverse resource allocation scheduling
  • D.utilizing the critical chair resources
查看答案
单选题

( )estimating is a technique for estimating the duration or cost of an activity ou project using historical data from a similar activity or project.

  • A.Parametric
  • B.Analogous
  • C.Three-point
  • D.Expert judgment
查看答案
单选题

The deliverable from this phase also includes the ( ) for the proposed system.

  • A.hardware and software specification
  • B.system performance specification
  • C.formal requirements definition
  • D.general problem statement
查看答案
单选题

Documentation of a software package is normally produced for two purposes. One is to explain the ( ) of the software and describe how to use them.

  • A.plans
  • B.cost
  • C.features
  • D.schedules
查看答案
单选题

Your company CEO just sent you an E-mail asking you to make a …on your project,which has been in progress for 10 months,to allIdentified internal and external stakeholders. He scheduled the presentation for next Monday.You expect more than 50 people to attenD.The first step in preparing the presentation is to ( ) .

  • A.define the audience
  • B.determine the objective
  • C.decide on the general form of the presentation
  • D.plan A.presentation strategy
查看答案
单选题

( ) is a property of object-oriented software by which an abstract operation may be performed in different ways in different classes.

  • A.MethoD
  • B.Polymorphism
  • C.Inheritance
  • D.Encapsulation
查看答案