根据你所学的项目管理知识,回答问题1至问题3,将解答填入答题纸的对应栏内。
【问题1】(5分)
配置管理包括哪六个主要活动?
【问题2】(5分)
关于受控库的权限设置,请按说明,不用打对号,只打叉号即可(只有全对才能得4分,其它0分)。
【问题3】(5分)
关于产品库的权限设置,请按说明,不用打对号,只打叉号即可(只有全对才能得4分,其它0分)。
【问题1】(5分)
配置管理包括6个主要活动:制定配置管理计划、配置标识、配置控制、配置状态报告、配置审计、发布管理和交付
【问题2】(5分)
【问题3】(5分)
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
In project human resource management , ( )is not a source of power for the project manager.
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
( )is a grid that shows the project resources assigned to each work package.
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
某公司投资一个使用寿命为5年的项目,第一年年初投入1000万元,从第1年到第5年每年年末都有净现金流量300万元。则项目的静态投资回收期为( )年。
下图是某地的街区网络图(单位:)里),疫情防控期间,一辆消毒车从疾控中心出发,需要消杀所有的街道并返回疾控中心。该消毒车完成消杀工作至少需要运行( )公里 。
某公司有东部、中部、西部三个生产基地,生产的产品需要运送带甲、乙、丙、丁四个市场,从生产基地到各个市场的单位运价及产量和需求量如表所示,完成该运输任务所需的最小运费为( )。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购15吨,乙处采购( )吨。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购( )吨,乙处采购20吨。