下表给出了某信息化建设项目到2019年8月1日为止的成本执行(绩效)数据,如果当前的成本偏差是非典型的,则完工估算(EAC) 为( )元。
本题考查EAC计算。
PV=121000,AC=12200,EV=2000+1600+2500+1500*80%+2000*75%+2500*60%=10300
EAC=AC+ETC 非典型偏差,则有:EAC=AC+(BAC-EV)=12200+50000-10300=51900
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
In project human resource management , ( )is not a source of power for the project manager.
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
( )is a grid that shows the project resources assigned to each work package.
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
某公司投资一个使用寿命为5年的项目,第一年年初投入1000万元,从第1年到第5年每年年末都有净现金流量300万元。则项目的静态投资回收期为( )年。
下图是某地的街区网络图(单位:)里),疫情防控期间,一辆消毒车从疾控中心出发,需要消杀所有的街道并返回疾控中心。该消毒车完成消杀工作至少需要运行( )公里 。
某公司有东部、中部、西部三个生产基地,生产的产品需要运送带甲、乙、丙、丁四个市场,从生产基地到各个市场的单位运价及产量和需求量如表所示,完成该运输任务所需的最小运费为( )。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购15吨,乙处采购( )吨。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购( )吨,乙处采购20吨。