某软件项目的活动图如下所示。图中顶点表示项目里程碑,连接顶点的边表示包含的活动,则里程碑(请作答此空 )在关键路径上,活动FG的松弛时间为( )。
关键路径是图中从起点到终点长度最长的那条路径,而关键路径的长度则是整个项目的工期。在本题中,路径START-D-F-H-FINISH的长度为48,是最长的一条路径,因此其是关键路径,因此D点是关键路径上的里程碑。
要求活动的松弛时间,就要求出活动的最早开始时间和最晚开始时间,其最晚开始时间减去最早开始时间,就是活动的松弛时间。对于活动FG,其最早开始时间是10+8=18,而最晚开始时间48-7-3=38,因此该活动的松弛时间是20。
Advancements in ( )have contributed to the growth of the automotive industry through the creation and evolution of self-driving vehicles.
In project human resource management , ( )is not a source of power for the project manager.
At the project establishment stage , the feasibility study mainly includes techinical feasibility analysis , ( ), operation environment feasibility analysis and other aspects of feasibility analysis.
( )is a grid that shows the project resources assigned to each work package.
Xinhua News Agency reported in January 2022,Chian will further promote the developmet of a digital economy during the 14th Five-Year Plan eriod(2021-2025). The plan also emphasized industrial ( )transformation.
某公司投资一个使用寿命为5年的项目,第一年年初投入1000万元,从第1年到第5年每年年末都有净现金流量300万元。则项目的静态投资回收期为( )年。
下图是某地的街区网络图(单位:)里),疫情防控期间,一辆消毒车从疾控中心出发,需要消杀所有的街道并返回疾控中心。该消毒车完成消杀工作至少需要运行( )公里 。
某公司有东部、中部、西部三个生产基地,生产的产品需要运送带甲、乙、丙、丁四个市场,从生产基地到各个市场的单位运价及产量和需求量如表所示,完成该运输任务所需的最小运费为( )。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购15吨,乙处采购( )吨。
某炼油厂每季度需供应合同单位汽油15吨,煤油12吨,重油12吨,该厂从甲乙两处运回原油提炼,已知两处炼油成分如表所示,从甲处采购原油价格为2000元/吨,乙处为2900元/吨,为了使成本最低,炼油厂应从甲处购( )吨,乙处采购20吨。